West Valley College Projects

West Valley Projects

Construction projects and progress.

Facilities Master Plan

Version: 2020

Construction Updates | September 2024

Design

At-a-Glance

Original Base Contract Amount $39,699,200
Project Phase Design
Percent Complete Design – 100%
Funding Measure W, State Funding
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2024
DSA Approval (Estimated) September 2024
Board Award April 2025
Construction Start June 2025
Construction Completion TBD
Closeout TBD
Move-in TBD

Key Contracts

Architect DLR
Contractor TBD
Project Manager Kitchell

Past Month’s Accomplishments

  • Meeting with DSA to discuss structural review comments

Next Month’s Milestones

  • Revise design and calculations to address all Structural review comments
  • DSA Backcheck to be scheduled for final review early November.
  • Continued construction work on Swing Space in Art Labs

Cost/Scope/Timeline Changes

  • State approval for funding is required and will delay the ability to start construction.

At-a-Glance

Original Base Contract Amount $23,602,700
Project Phase Design
Percent Complete Design – 100%
Funding Measure W
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2024
DSA Approval (Estimated) September 2024
Board Award April 2025
Construction Start June 2025
Construction Completion TBD
Closeout TBD
Move-in TBD

Key Contracts

Architect DLR
Contractor TBD
Project Manager Kitchell

Past Month’s Accomplishments

  • Meet with DSA to discuss structural review comments

Next Month’s Milestones

  • Revise design and calculations to address all structural review comments
  • DSA Backcheck to be scheduled for final review early November.

Cost/Scope/Timeline Changes

None at this time.

Planning

At-a-Glance

Original Base Contract Amount $92,015,700
Project Phase DBE Selection/Procurement
Percent Complete 0%
Funding Measure W
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Build Team Selection/Board Approval September 2024
Design Completion June 2025
DSA Approval February 2026
Construction Start June 2026
Construction Completion November 2027
Move-in March 2028
Closeout May 2028

Key Contracts

Design Build Company Hensel Phelps & Cannon
Project Manager Kitchell

Past Month’s Accomplishments

  • Board approval of Design Build Team Contract and Kitchell CM Contract for Phase 1
  • Kick off meeting held

Next Month’s Milestones

  • User meetings to refine design program

Cost/Scope/Timeline Changes

  • Includes WV-09 PE renovation budget/scope

Construction

At-a-Glance

Original Base Contract Amount $807,996.00
Project Phase Construction
Percent Complete 67%
Funding Community Support Funds
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion
DSA Approval N/A
Board Award June 18, 2024
Construction Start July 24, 2024
Construction Completion November 26, 2024
Closeout February 20, 2025
Move-in February 2025

Key Contracts

Architect ANLA
Contractor Redwood Engineering
Project Manager Kitchell

Past Month’s Accomplishments

  • Existing landscape irrigation removal completed
  • Grading completed
  • Irrigation installation completed
  • Started boulder delivery
  • Trees planted

Next Month’s Milestones

  • Landscaping and hardscape will be completed
  • Boulder placement will be completed
  • Soil prep and planting will continue
  • Permalok forming will start

Cost/Scope/Timeline Changes

  • Construction date delayed one month due to contractor issues.

At-a-Glance

Original Base Contract Amount $2,024,306.72
Project Phase Construction
Percent Complete 78%
Funding Community Support Funds
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 1, 2024
DSA Approval N/A
Board Award May 14, 2024
Construction Start July 8, 2024
Construction Completion January 15, 2025
Closeout January 15, 2025
Move-in N/A

Key Contracts

Architect Garland Roofing
Contractor Western Roofing
Project Manager Kitchell

Past Month’s Accomplishments

  • Contractor completed roof replacement on Administration Building
  • Contractor has begun the demolition and installation of roof at IS Building

Next Month’s Milestones

  • Complete IS and College of Adaptive Arts Buildings
  • Receive all materials for remaining roofs

Cost/Scope/Timeline Changes

  • All of the existing framing for the mechanical roof screens has been replaced due to dry rot at the Administration building.

At-a-Glance

Original Base Contract Amount $15,817,821.75
Project Phase Construction – Multi-Prime
Percent Complete 74%
Funding Measure W
Total Change Order Amount $922,232.94
Percent of Approved Change Orders 5.83%

Schedule Milestones

Design Completion May 10, 2022
DSA Approval January 11, 2023
Board Award April 18, 2023 & July 18, 2023
Construction Start June 14, 2023
Construction Completion January 6, 2025
Closeout March 1, 2025
Move-in January 6, 2025

Key Contracts

Architect LPAS
Contractor McGuire & Hester, Smith & Sons, Ciari Plumbing, Smith MEP, SC Builders, Los Loza, Crusader Fence
Project Manager Kitchell

Past Month’s Accomplishments

  • Building electrical panels energized
  • Mechanical rough in completed
  • Window install completed
  • Tile install began
  • Painting began

Next Month’s Milestones

  • Tile install will be complete
  • Painting will be complete
  • Plumbing trim out will begin
  • Mechanical trim out will begin
  • Electrical/low voltage trim out will begin
  • Mechanical unit startup will occur
  • Metal wall panels will complete

Cost/Scope/Timeline Changes

  • Additional cost to replace some of the existing site light poles with a new district standard

At-a-Glance

Original Base Contract Amount $59,234,092
Project Phase Construction
Percent Complete 61%
Funding Measure C, Measure W, State Funding
Total Change Order Amount $4,159.464.44
Percent of Approved Change Orders 9.5%

Schedule Milestones

Design Completion February 26, 2021
DSA Approval January 21, 2022
Board Award October 18, 2022
Construction Start January 26, 2023
Construction Completion September 15, 2025
Closeout October 15, 2025
Move-in November 2025

Key Contracts

Architect ABA/MCA
Contractor Swinerton
Project Manager Kitchell

Past Month’s Accomplishments

  • South Tower Top Out
  • Sector 3 Roofing Complete
  • Interior Wall MEP Sign Off Sector 1 & 2
  • Beam Signing Event

Next Month’s Milestones

  • Exterior Stucco
  • Exterior Glazing Install
  • Sector 3 MEP Rough In & Framing

Cost/Scope/Timeline Changes

  • Fireproofing removal and new fireproofing install will impact the project and cause project delays.