West Valley College Projects

West Valley Projects

Construction projects and progress.

Facilities Master Plan

Version: 2020

Construction Updates | July 2024

At-a-Glance

Original Base Contract Amount $59,234,092
Project Phase Construction
Percent Complete 50%
Funding Measure C, Measure W, State Funding
Total Change Order Amount $3,627,780.46
Percent of Approved Change Orders 6.4%

Schedule Milestones

Design Completion February 26, 2021
DSA Approval January 21, 2022
Board Award October 18, 2022
Construction Start January 26, 2023
Construction Completion September 15, 2025
Closeout December 15, 2025
Move-in November 15 2025

Key Contracts

Architect ABA/MCA
Contractor Swinerton
Project Manager Kitchell

Past Month’s Accomplishments

  • Interior Wall Mechanical/Electrical & Plumbing
  • Interior Framing & Sheathing
  • Curtain Wall Progress
  • Sector 3 Roofing Start

Next Month’s Milestones

  • South Tower Top Out
  • Sector Elevated Slab Work
  • Sector 3 Roofing Complete

Cost/Scope/Timeline Changes

  • Fireproofing removal and new fireproofing install will impact the project and cause project delays.

At-a-Glance

Original Base Contract Amount $15,817,821.75
Project Phase Construction – Multi-Prime
Percent Complete 59%
Funding Measure W
Total Change Order Amount $751,450.50
Percent of Approved Change Orders 4.75%

Schedule Milestones

Design Completion May 10, 2022
DSA Approval January 11, 2023
Board Award April 18, 2023 & July 18, 2023
Construction Start June 14, 2023
Construction Completion December 31, 2024
Closeout March 1, 2025
Move-in December 31, 2024

Key Contracts

Architect LPAS
Contractor McGuire & Hester, Smith & Sons, Ciari Plumbing, Smith MEP, SC Builders, Los Loza, Crusader Fence
Project Manager Kitchell

Past Month’s Accomplishments

  • Exterior Plaster completed.
  • Rough grading completed.
  • Framing completed.
  • Plumbing rough in completed.

Next Month’s Milestones

  • Roofing will be complete.
  • Building electrical panels will energize.
  • Site concrete will begin.
  • Insulation will be complete.
  • Drywall will be complete.
  • Electrical rough in will be complete.
  • Mechanical rough in will be complete.

Cost/Scope/Timeline Changes

  • Additional cost to replace some of the existing site light poles with a new district standard.
  • Costs associated with changes to the building’s security system

At-a-Glance

Original Base Contract Amount $689,800
Project Phase Construction
Percent Complete 0%
Funding Community Support Funds
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion
DSA Approval N/A
Board Award June 18, 2024
Construction Start July 24, 2024
Construction Completion November 26, 2024
Closeout February 20, 2025
Move-in February 2025

Key Contracts

Architect ANLA
Contractor Redwood Engineering
Project Manager Kitchell

Past Month’s Accomplishments

  • Contract executed, Notice to Proceed Issued
  • Contractor mobilized equipment, material

Next Month’s Milestones

  • Demolition of existing landscape
  • Grading of landscape area

Cost/Scope/Timeline Changes

  • Construction date delayed one month due to contract issues.

At-a-Glance

Original Base Contract Amount $23,602,700
Project Phase Design
Percent Complete Design – 100%
Funding Measure W
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2024
DSA Approval August 2024
Board Award March 2025
Construction Start June 2025
Construction Completion TBD
Closeout TBD
Move-in TBD

Key Contracts

Architect DLR
Contractor TBD
Project Manager Kitchell

Past Month’s Accomplishments

  • Continued collaboration with DSA to address their comments during approval process.
  • Fire/Life/Safety and Access review is almost complete.
  • Structural review in progress.
  • Music relocation to Swing Space in Cilker Bldg.

Next Month’s Milestones

  • Anticipation of DSA approval.

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $39,699,200
Project Phase Design
Percent Complete Design – 100%
Funding Measure W, State Funding
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2024
DSA Approval August 2024
Board Award March 2025
Construction Start June 2025
Construction Completion TBD
Closeout TBD
Move-in TBD

Key Contracts

Architect DLR
Contractor TBD
Project Manager Kitchell

Past Month’s Accomplishments

  • Continued collaboration with DSA to address their comments during approval process.
  • Fire/Life/Safety and Access review is almost complete.
  • Structural review in progress.

Next Month’s Milestones

  • Anticipation of DSA approval
  • Continued construction work on Swing Space in Art Labs

Cost/Scope/Timeline Changes

  • This project will require State approval for funding as well which will delay the ability to start construction.

At-a-Glance

Original Base Contract Amount $92,015,700
Project Phase DBE Selection/Procurement
Percent Complete 0%
Funding Measure W
Total Change Order Amount N/A
Percent of Approved Change Orders 0%

Schedule Milestones

Design Build Team Selection/Board Approval September 2024
Design Completion June 2025
DSA Approval February 2026
Construction Start June 2026
Construction Completion November 2027
Move-in March 2028
Closeout May 2028

Key Contracts

Design Build Company TBD
Project Manager Kitchell

Past Month’s Accomplishments

  • Design Build Proposals reviewed in July
  • Final interviews with Design Build Teams

Next Month’s Milestones

  • Selection of Design Build Team
  • Prepare Design Build Team Contract for Board approval in September

Cost/Scope/Timeline Changes

  • Includes WV-09 PE renovation budget/scope