Skip to main content

Mission College Projects

Mission Projects

Construction projects and progress.

Facilities Master Plan

Version: May 2018

Construction Updates | July 2024

At-a-Glance

Original Base Contract Amount $16,018,622
Project Phase Construction
Percent Complete 0%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion March 2023
DSA Approval February 2024
Board Award June 2024
Construction Start July 2024
Construction Completion September 2025
Closeout October 2025
Move-in Summer 2025

Key Contracts

Architect WRNS
Contractor SC Builders
Project Manager Gilbane

Past Month’s Accomplishments

  • Notice to Proceed issued
  • Pre-Construction Meeting

Next Month’s Milestones

  • Site Walk with Owner O&M to identify utility shut-off valve locations
  • Start of Construction – fencing installation

Cost/Scope/Timeline Changes

N/A

At-a-Glance

Original Base Contract Amount $55,000,000
Project Phase Pre-Construction
Percent Complete Design – 95%
Funding Measure W and State Funding
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion June 2023
DSA Approval November 2023
Board Award October 2024
Construction Start November 2024
Construction Completion November 2026
Closeout February 2026
Move-in Winter 2026

Key Contracts

Architect LPA
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • AV package review is in progress.

Next Month’s Milestones

  • LPA to complete addendum #1
  • LPA to submit addendum #1 to DSA

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $3,743,505
Project Phase Construction
Percent Complete 0%
Funding Measure W and State Funding
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Completion
DSA Approval
Board Award May 2024
Construction Start July 2024
Construction Completion January 2025
Closeout February 2025
Move-in Winter 2025

Key Contracts

Architect Garland
Contractor Western Roofing Service
Project Manager Gilbane/Kitchell

Past Month’s Accomplishments

  • Coating materials were delivered
  • Science roof restoration started

Next Month’s Milestones

  • Science roof restoration complete
  • Campus Center roof restoration to start

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $6,442,000
Project Phase Closeout
Percent Complete 98%
Funding Measure W
Total Change Order Amount $538,850
Percent of Approved Change Orders 8%

Schedule Milestones

Design Completion November 2020
DSA Approval September 2021
Board Award December 2021
Construction Start December 2021
Construction Completion August 2023
Closeout September 2023
Move-in September 2023

Key Contracts

Architect Anderson Brule Architects
Contractor EF Brett & Company
Project Manager Gilbane Building Company

Past Month’s Accomplishments

Installation and programming of emergency pull down station completed.

Next Month’s Milestones

  • Final Security Testing and Commissioning

Cost/Scope/Timeline Changes

N/A

At-a-Glance

Original Base Contract Amount $669,000
Project Phase Construction
Percent Complete 99%
Funding Measure W
Total Change Order Amount $7,742
Percent of Approved Change Orders 1.16%

Schedule Milestones

Design Completion February 2023
DSA Approval June 2023
Board Award December 2023
Construction Start February 2024
Construction Completion June 2024
Closeout July 2024
Move-in August 2024

Key Contracts

Architect WRNS
Contractor Environmental Systems
Project Manager Gilbane

Past Month’s Accomplishments

  • Collect all warranties and O&M manuals
  • Commissioning Pre-Check
  • Paint Hydronic Lines

Next Month’s Milestones

  • Final commissioning

Cost/Scope/Timeline Changes

  • N/A

At-a-Glance

Original Base Contract Amount $10,242,828
Project Phase Construction
Percent Complete 97%
Funding Measure W
Total Change Order Amount $2,460,484.87
Percent of Approved Change Orders 24%

Schedule Milestones

Design Completion February 2021
DSA Approval February 2022
Board Award May 2019
Construction Start
Construction Completion November 2023
Closeout May 2024
Move-in May 2024

Key Contracts

Architect CURRENT Design Group
Contractor SunPower
Project Manager Gilbane

Past Month’s Accomplishments

  • Cold Commissioning completed

Next Month’s Milestones

  • Hot Commissioning to start.
  • SVP to issue permission to operate.
  • Solar system in Lot C to be energized.

Cost/Scope/Timeline Changes

  • Relocation of Capacitor Bank

At-a-Glance

Original Base Contract Amount $2,842,000
Project Phase Closeout
Percent Complete 100%
Funding Measure W
Total Change Order Amount $273,624
Percent of Approved Change Orders 9.63%

Schedule Milestones

Design Completion March 2021
DSA Approval September 10, 2021
Board Award March 15, 2022
Construction Start March 2022
Construction Completion February 2024
Closeout February 2024
Move-in April 2023

Key Contracts

Architect WRNS
Contractor Suarez & Munoz
Project Manager Gilbane

Past Month’s Accomplishments

N/A

Next Month’s Milestones

  • Issuance of Notice of Completion

Cost/Scope/Timeline Changes

N/A

At-a-Glance

Original Base Contract Amount TBD
Project Phase Design
Percent Complete 0%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming May 2024
Design Phase
DSA Submission
Board Award
Construction Start
Construction Completion
Closeout
Move-in

Key Contracts

Architect P2S
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Existing Geothermal field condition assessment walk held

Next Month’s Milestones

  • District review of repair project scope from EOR
  • RFP/RFQ document creation

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $1,000,000
Project Phase Bidding
Percent Complete 0%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Design Phase July 2024
DSA Submission July 2026 | July 2027
Bid Phase August 2024 | November 2024
Board Award November 2024
Construction Start December 2024
Construction Completion September 2025
Closeout October 2025
Move-in

Key Contracts

Architect SVA Architects
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Bid Calendar Approved

Next Month’s Milestones

  • Creation of PlanetBids opportunity

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $19,229,400
Project Phase Design
Percent Complete 0%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming August 2024
Design Build RFP/RFQ November 2024 | June 2025
Board Award July 2025
Design Phase August 2025 | May 2026
DSA Submission June 2026 | March 2027
Construction Start April 2027
Construction Completion October 2028
Closeout November 2028
Move-in Winter 2028

Key Contracts

Architect TBD
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Project Programming meetings started

Next Month’s Milestones

  • Project definition established
  • RFP/RFQ document creation

Cost/Scope/Timeline Changes

None at this time.

At-a-Glance

Original Base Contract Amount $72,244,800
Project Phase Design
Percent Complete 0%
Funding Measure W
Total Change Order Amount $0
Percent of Approved Change Orders 0%

Schedule Milestones

Programming May 2024
Design Build RFP/RFQ September 2024 | April 2024
Board Award May 2025
Design Phase June 2025 | June 2026
DSA Submission July 2026 | July 2027
Construction Start August 2027
Construction Completion August 2029
Closeout November 2029
Move-in Winter 2029

Key Contracts

Architect TBD
Contractor TBD
Project Manager Gilbane

Past Month’s Accomplishments

  • Project Programming meetings started

Next Month’s Milestones

  • Project definition established
  • RFP/RFQ document creation

Cost/Scope/Timeline Changes

None at this time.