Mission Projects
Construction projects and progress.
Facilities Master Plan
Version: May 2018
Construction Updates | September 2024
Design
At-a-Glance
Original Base Contract Amount | $72,244,800 |
Project Phase | Design |
Percent Complete | Programming |
Funding | Measure W |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Programming | May 2024 |
Design Build RFP/RFQ | November 2024 | June 2025 |
Board Award | July 2025 |
Design Phase | July 2025 |
DSA Submission | August 2026 | August 2027 |
Construction Start | September 2027 |
Construction Completion | September 2029 |
Closeout | December 2029 |
Move-in | Winter 2029 |
Key Contracts
Architect | TBD (DBE) |
Contractor | TBD (DBE) |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Project Programming meetings started
Next Month’s Milestones
- Project definition established
- RFP/RFQ document creation
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount | $19,229,400 |
Project Phase | Design |
Percent Complete | Programming |
Funding | Measure W |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Programming | August 2024 |
Design Build RFP/RFQ | March 2025 | October 2025 |
Board Award | November 2025 |
Design Phase | January 2026 | October 2026 |
DSA Submission | November 2026 | April 2027 |
Construction Start | May 2027 |
Construction Completion | November 2028 |
Closeout | December 2028 |
Move-in | Winter 2028 |
Key Contracts
Architect | TBD (DBE) |
Contractor | TBD (DBE) |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Project Programming meetings started
Next Month’s Milestones
- Project definition established
- RFP/RFQ document creation
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount | TBD |
Project Phase | Design |
Percent Complete | Programming |
Funding | Community Support Funds |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Programming | May 2024 |
Design Phase | |
DSA Submission | |
Board Award | |
Construction Start | |
Construction Completion | |
Closeout | |
Move-in |
Key Contracts
Architect | P2S |
Contractor | TBD |
Project Manager | Gilbane |
Past Month’s Accomplishments
- District review of repair project scope from EOR
Next Month’s Milestones
- EOR monitoring building usage for mechanical reporting/ design
Cost/Scope/Timeline Changes
None at this time.
Pre-Construction
At-a-Glance
Original Base Contract Amount | $1,400,000 |
Project Phase | Bidding |
Percent Complete | 100% |
Funding | Measure W |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Design Completion | August 2024 |
DSA Approval | June 2024 |
Board Award | January 2025 |
Construction Start | February 2025 |
Construction Completion | November 2025 |
Closeout | December 2025 |
Move-in |
Key Contracts
Architect | SVA Architects |
Contractor | TBD |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Approval of DSA Addendum
Next Month’s Milestones
- Close of Public Bid Effort
Cost/Scope/Timeline Changes
None at this time.
At-a-Glance
Original Base Contract Amount | $55,000,000 |
Project Phase | Pre-Construction |
Percent Complete | Bidding |
Funding | Measure W and State Funding |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Design Completion | June 2023 |
DSA Approval | November 2023 |
Board Award | November 2024 |
Construction Start | February 2025 |
Construction Completion | February 2027 |
Closeout | March 2027 |
Move-in | March 2027 |
Key Contracts
Architect | LPA |
Contractor | TBD |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Contract documents uploaded on PlanetBids.
Next Month’s Milestones
- Bid opening on September 17, 2024.
Cost/Scope/Timeline Changes
- N/A
Construction
At-a-Glance
Original Base Contract Amount | $3,743,505 |
Project Phase | Construction |
Percent Complete | 69% |
Funding | Measure W and State Funding |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Design Completion | |
DSA Approval | |
Board Award | May 2024 |
Construction Start | July 2024 |
Construction Completion | January 2025 |
Closeout | February 2025 |
Move-in | February 2025 |
Key Contracts
Architect | Garland |
Contractor | Western Roofing Service |
Project Manager | Gilbane/Kitchell |
Past Month’s Accomplishments
- TAV, Science and Campus Center buildings completed.
Next Month’s Milestones
- Hospitality Management and Locker Rooms to complete.
Cost/Scope/Timeline Changes
- N/A
At-a-Glance
Original Base Contract Amount | $16,018,622 |
Project Phase | Construction |
Percent Complete | 5% |
Funding | Measure W |
Total Change Order Amount | $0 |
Percent of Approved Change Orders | 0% |
Schedule Milestones
Design Completion | March 2023 |
DSA Approval | February 2024 |
Board Award | June 2024 |
Construction Start | July 2024 |
Construction Completion | September 2025 |
Closeout | October 2025 |
Move-in | Winter 2025 |
Key Contracts
Architect | WRNS |
Contractor | SC Builders |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Start of Construction Demolition
- MEP Safe-off
Next Month’s Milestones
- MEP Layout
- SOG Trenching
Cost/Scope/Timeline Changes
N/A
At-a-Glance
Original Base Contract Amount | $10,242,828 |
Project Phase | Construction |
Percent Complete | 97% |
Funding | Measure W |
Total Change Order Amount | $2,460,484.87 |
Percent of Approved Change Orders | 24% (DBE) |
Schedule Milestones
Design Completion | February 2021 |
DSA Approval | February 2022 |
Board Award | May 2019 |
Construction Start | |
Construction Completion | November 2023 |
Closeout | May 2024 |
Move-in | May 2024 |
Key Contracts
Architect | CURRENT Design Group |
Contractor | SunPower |
Project Manager | Gilbane |
Past Month’s Accomplishments
- The water lines investigation completed.
Next Month’s Milestones
- SVP to issue permission to operate.
- Hot Commissioning to start.
- Solar system in Lot C to be energized.
Cost/Scope/Timeline Changes
- Relocation of Capacitor Bank
Closeout
At-a-Glance
Original Base Contract Amount | $669,000 |
Project Phase | Closeout |
Percent Complete | 100% |
Funding | Measure W |
Total Change Order Amount | $7,742 |
Percent of Approved Change Orders | 1.16% |
Schedule Milestones
Design Completion | February 2023 |
DSA Approval | June 2023 |
Board Award | December 2023 |
Construction Start | February 2024 |
Construction Completion | June 2024 |
Closeout | July 2024 |
Move-in | August 2024 |
Key Contracts
Architect | WRNS |
Contractor | Environmental Systems |
Project Manager | Gilbane |
Past Month’s Accomplishments
- Turnover Cx report to owner
Next Month’s Milestones
- Prepare Notice of Completion
Cost/Scope/Timeline Changes
- N/A
At-a-Glance
Original Base Contract Amount | $6,442,000 |
Project Phase | Closeout |
Percent Complete | 98% |
Funding | Measure W |
Total Change Order Amount | $538,850 |
Percent of Approved Change Orders | 8% |
Schedule Milestones
Design Completion | November 2020 |
DSA Approval | September 2021 |
Board Award | December 2021 |
Construction Start | December 2021 |
Construction Completion | August 2023 |
Closeout | September 2023 |
Move-in | September 2023 |
Key Contracts
Architect | Anderson Brule Architects |
Contractor | EF Brett & Company |
Project Manager | Gilbane Building Company |
Past Month’s Accomplishments
- Correction of the security system from pre-punch list
Next Month’s Milestones
- Final Security testing
Cost/Scope/Timeline Changes
N/A