Project Progress Report
West Valley College
Project Status:
•Users meeting ongoing
•Classroom layouts and faculty offices
approved by users and executive cabinet.
•Design drawing and phasing options were
approved October 2010
•Working/construction drawings started
October 2010
•Project LEED Certified
•Drawing submitted to DSA for approval
January 2011
Completed This Period
Activity Planned for Next Period
Schedule Summary
IPP Submittal:10/2008
FPP Submittal:07/2009
Preliminary Plans:07/2011
Working Drawings:03/2012
DSA Submittal:12/2012
DSA Approval:05/2013
Bid:11/2013
Award of Bid:12/2013
Begin Construction:02/2014
End Construction:02/2015
DSA Closeout:
Budget Summary
Funding Source
Measure H$7,442,515
State Funds$6,150,233
Project Budget$13,582,748
Encumbered
Expenditures
Budget Balance$13,582,748
Construction Budget$9,985,023
Bid Awards
Executed C/Os
Construction Balance$9,985,023