Project Progress Report  Mission College  

 

Project Status:

  • Scope of work planned for completion at the same time as project MC 34.
  • Board approval of Sandis' electrical/civil contract completed on April 16, 2009
  • Anticipate coordination of users meetings to address scope and schedule through out summer 2009
  • Project Phase estimated completion: 10%

Completed This Period 

  • SOI distribution to the District's Pool of Architects
  • Board approval of architect firm April 2009

Activity Planned for Next Period

  • Commence Preliminary Plans to be completed by August 2009.
  • DSA submittal August/September 2009
  • Estimated DSA approval November/December 2009
Schedule Summary

IPP Submittal:03/2009 

FPP Submittal:04/2009 

Preliminary Plans:06/2009 

Working Drawings:07/2009 

DSA Submittal:09/2009 

DSA Approval:11/2009 

Bid:12/2009 

Award of Bid:02/2010 

Begin Construction:03/2010 

End Construction:08/2010 

DSA Closeout:09/2010 

Budget Summary

Funding Source

Measure H$1,771,721 

State Funds 

Project Budget$1,771,721 

Encumbered$100,611 

Expenditures 

Budget Balance$1,671,110 

Construction Budget$1,316,635 

Bid Awards 

Executed C/Os 

Construction Balance$1,316,635