Project Progress Report  District  

dist_fire_alarm_replace  

Project Status:

  • Preliminary Plans funds were scheduled for release by Department of Finance in November/December, 2008
  • Board of Trustees approved engineer contract December 2008
  • Estimated Completion of Pre-Design Phase: 95%

Completed This Period 

  • RFQ submittals received September 5, 2008
  • Interviews for selection of Electrical Engineering firm scheduled for October 8, 2008
  • Board approval of contract on December 6, 2008

Activity Planned for Next Period

  • Receive State funding for preliminary plans phase and commence the design phase with both Colleges.
  • Project on hold due to State Budget Crisis
Schedule Summary

IPP Submittal:07/2005 

FPP Submittal:07/2006 

Preliminary Plans:11/2008 

Working Drawings:on hold 

DSA Submittal: 

DSA Approval: 

Bid: 

Award of Bid: 

Begin Construction: 

End Construction: 

DSA Closeout: 

Budget Summary

Funding Source

Measure H$685,048 

State Funds$13,000,000 

Project Budget$13,685,048 

Encumbered$83 

Expenditures$83 

Budget Balance$13,684,965 

Construction Budget$10,384,000 

Bid Awards 

Executed C/Os 

Construction Balance$10,384,000