Project Progress Report
West Valley College
Project Status:
•Building construction is in
two
phases:
- Phase I started Fall 2009 and finished
Fall
2010
- Phase II start Fall 2010 and will
finish Fall 2011
• Phase
I is complete.
- Classes have been in session since Fall 2010
• Phase
II hazmat abatement complete
• Phase
II construction started October 2010.
Completed This Period
Activity Planned for Next Period
Schedule Summary
IPP Submittal:N/A
FPP Submittal:N/A
Preliminary Plans:12/2007
Working Drawings:01/2008
DSA Submittal:04/2008
DSA Approval:06/2008
Bid:06/2008
Award of Bid:06/2008
Begin Construction:06/2008
End Construction:12/2008
DSA Closeout:03/2009
Budget Summary
Funding Source
Measure H$8,085,029
State Funds
Project Budget$8,085,029
Encumbered$4,321,024
Expenditures$3,506,160
Budget Balance$3,764,005
Construction Budget$6,200,000
Bid Awards$3,390,873
Executed C/Os$263,844
Construction Balance$2,809,127